Piedmont Water Company is advancing a $22 million expansion of the Carey Station Water Reclamation Facility as part of its long-term strategy to strengthen system capacity, enhance reliability, and support continued growth across the Greene County communities.
This project represents a significant capital investment in the infrastructure that increases the capacity of the plant from half a million gallons per day to 1.5 million gallons per day, protecting public health, the environment, and economic development throughout our service area.
Facilities like Carey Station require years of planning, engineering, permitting, and financial commitment before construction even begins. These investments ensure our systems remain resilient, compliant with regulatory standards, and capable of meeting future demand.
Construction Progress
Construction activity is now well underway, with crews completing critical sitework infrastructure to prepare the facility for the next stages of development. Upcoming phases will include site piping and the installation of synthetic liners for storage ponds.




Progress to date includes:
- Installation of sediment basins and erosion-control measures to manage stormwater during construction
- Excavation and shoring for the installation of the new equalization influent pump station wet well and valve pit structures
- Rough grading of the equalization storage basin
- Rough grading of the reject storage basin
These foundational improvements form the backbone of the expanded treatment system and are essential for safe, efficient, and environmentally compliant operation.
Why Investments Like This Matter
Wastewater infrastructure is largely unseen by the public, but it is one of the most critical services supporting daily life. Expansions like the Carey Station project require substantial funding for:
- Engineering and design
- Environmental studies and regulatory permitting
- Specialized construction and materials
- Long-term operations and maintenance planning
By investing proactively, Piedmont Water helps prevent capacity shortages, reduce the risk of service interruptions, and avoid emergency repairs that can be more costly for customers in the long run.
“This project reflects our commitment to investing ahead of growth,” said Brent Hurst, Chief Operating Officer of Piedmont Water Company. “By expanding capacity now, we’re ensuring reliable service for our customers today and for generations to come.”
Looking Ahead
Once complete, the upgraded Carey Station facility will provide increased treatment capacity, improved operational efficiency, and long-term resilience for our wastewater system — positioning our communities for sustainable growth well into the future.
Piedmont Water will continue providing updates as construction progresses and key milestones are reached.